Simulation Notice: This is an educational adaptation of Atlassian JIRA's interface, built so you can explore Scrum board data and generate reports without a paid JIRA subscription. The data, stories, and sprint history are fabricated for the Marchex Call Analytics case study. Chart behavior mirrors real JIRA reports.

Sprint Board

Project Backlog

Sprint Reports

Velocity Chart

Shows story points committed vs. completed for each sprint. A healthy team has a small, consistent gap. A growing gap indicates planning or execution problems.

Velocity chart: Sprint 1 committed 30/completed 28, Sprint 2 30/22, Sprint 3 28/15, Sprint 4 25/5.

Sprint Burndown Chart

Shows remaining work within a single sprint plotted against time. The guideline shows ideal even progress. Flat sections mean no work was completed on those days.

Sprint burndown chart showing remaining story points over 10 days.

Cumulative Flow Diagram

Shows the count of work items in each status over time across all sprints. A widening "In Progress" band indicates growing WIP. A flattening "Done" band means throughput is declining.

Cumulative flow diagram showing To Do, In Progress, In Review, and Done item counts across 4 sprints.

Control Chart (Cycle Time)

Shows how many days each completed story took from "In Progress" to "Done." The rolling average line and standard deviation band reveal whether delivery time is stable or deteriorating.

Sprint 1 (circle) Sprint 2 (diamond) Sprint 3 (triangle) Sprint 4 (square)
Control chart showing cycle times ranging from 2-8 days for 19 completed stories across 4 sprints.